Day 49 & 50

August 24, 2018 09:26 UTC DV Team (LivingStyleGuide)Subscribe to this teams's activities

Violeta

  • Working on issue #17
  • Waiting for feedback on PR for #14

Diana

  • worked full day on RgSoc.
  • informed teammate, mentors and supervisor that i am back.
  • looked into new issues and create a todolist.
  • Created meeting with Bright (monday), Christina (tuesday) and have general meeting with supervisor and mentor on Thursday.
  • Working on Webproject file to install PIMD on example html project. & Discussed questions with Bright.
  • Updated changes for blog article.

TODO :
- Monday: Finish Webproject (tutorial) & update tutorial with missing steps.
- Continue with issues.
- upload blog article to RgSoc.