Day 5

July 6, 2018 16:53 UTC Team Rubies (if me - mental health communication app)Subscribe to this teams's activities

Tasks completed today

  • Wrote tests for checkbox.
  • We tried writing tests for radiobuttons but struggled with it. Hope to complete it on Monday.
  • We worked on PR #910 and #911.
  • During the day, Prateksha had problems with storybook, which is the UI development environment. We then realized that the last commit that was merged deleted important functions. We created an issue to fix this and sent a PR.
  • Videocall with supervisor, mentors, coaches.
  • Worked on Introduction blog post.

Things we learnt

To-Do

Comments

You must be logged in to add a comment.